From corporate tax registration to audits and bookkeeping, Young & Right offers personalized solutions that keep your business compliant and stress-free. Let’s take the complexity off your plate—starting with a free consultation.
Book Your Free Consultation
A contractor finishes a project worth AED 2 million. The developer certifies the work but keeps 10% as retention until the defects-liability period ends. Does the contractor account for VAT on the withheld AED 200,000 now, or only when the developer pays it? Getting this wrong can affect VAT returns, cash flow and customer reconciliations.
Construction contracts often include advances, milestones, progress invoices, variations and retention. VAT treatment follows the contract and statutory date-of-supply rules, not simply the date cash reaches the bank.
The FTA's Real Estate VAT Guide explains that construction services supplied in the UAE are generally subject to 5% VAT. For a straightforward supply, time-of-supply rules may refer to service completion, payment or invoice issuance. However, projects delivered over time with periodic payments or consecutive invoices can fall under the continuous-supply rules in Article 26 of the VAT Decree-Law.
For those arrangements, the relevant tax point generally arises at the earliest of issuing a tax invoice, the payment due date shown on the invoice, or receiving payment. Where none of the prescribed triggers occurs, the 12-month rule may become relevant. A project certification itself does not necessarily create a tax point, although certification may trigger a payment obligation that does.
Suppose a construction company receives an AED 100,000 advance against a commercial fit-out contract. The company cannot automatically wait until the final handover to consider VAT. Receipt of an advance can trigger the applicable time-of-supply rule for the amount received, and the accounting team must examine the invoice and contract terms.
Finance should distinguish true advance consideration from amounts that are genuinely refundable security deposits and have different legal substance. The label on a receipt is not enough; the payment's purpose, conditions and contractual treatment matter. Keep the bank receipt linked to the advance invoice and the later progress claims to avoid accounting for the same amount twice.
Retention is normally a portion of contract consideration held back pending completion confirmation or rectification of defects. The FTA guidance says there are no special standalone retention tax-point rules: businesses apply the relevant normal or continuous-supply provisions.
Where Article 26 applies, the FTA indicates that retention can trigger VAT when payment is received, a tax invoice is issued for the retention, or 12 months have elapsed from certification of completed work, as applicable. Under a single-supply analysis, the timing can be different, depending on when the services are contractually complete and other relevant events.
Therefore, a blanket policy of “charge VAT only when retention cash arrives” can be incorrect. Equally, charging VAT on every retention amount as soon as a milestone is certified may be premature. The contract, certification process and tax-point analysis should be documented.
Example: AED 500,000 milestone with 10% retention
Assume a project has an AED 500,000 milestone before VAT and a 10% contractual retention. The gross payment expected immediately might be AED 450,000, with AED 50,000 retained. The VAT calculation and timing cannot be determined from those figures alone. Finance must establish whether the milestone creates a tax point for the full amount, whether the retention is separately invoiced and what the contract says about completion and payment due dates.
A useful worksheet lists the certified amount, prior advances, current amount due, retention withheld, invoiced value, VAT recognised and net cash collected. That creates a traceable explanation when a developer's payment certificate differs from the supplier's tax invoice.
Recording VAT solely from bank deposits. Cash received may exclude retention or include advances relating to a future stage.
Ignoring payment due dates. A contractual or invoiced due date can matter even if the customer pays late.
Treating certifications as tax invoices. A certificate provides evidence of work but is not automatically a compliant tax invoice.
Duplicating VAT on advances. An advance already accounted for must be reconciled against the later stage billing.
Failing to track variations and credit notes. Approved changes can affect contract value, VAT calculations and the final account.
Maintain a contract-by-contract register showing the total contract amount, advance balance, certified work, invoices, VAT, retention receivable and collections. Reconcile that register with accounts receivable, the general ledger and the VAT return. If projects are managed through subcontractors, check purchase invoices and input VAT separately; a subcontractor's VAT claim does not follow automatically from the main contractor's billing schedule.
Review contracts with the tax adviser when clauses are unusual, projects cross periods or the parties dispute completion. Early review often prevents expensive retrospective corrections.
Young & Right Accounting & Tax Consultancy helps UAE contractors, developers and project-based businesses review tax invoices, retention schedules, VAT returns and contract accounting. Clear VAT timing helps companies report accurately while maintaining visibility over money still owed by customers.
Next step: Request a construction VAT reconciliation before filing your next return.
Get expert guidance on VAT treatment for retention payments, advance payments, and tax points in the UAE.
Get Expert VAT Support